The contractor will be working this Saturday, April 23, 2022 from 8:00AM to 5:00PM to continue drilling the Geopier foundations. The work will all be performed onsite and the equipment noise is not expected to impact the surrounding area and should only heard within the project site. If you have any questions, please contact us at RecCenterBuild@sanbruno.ca.gov.
March 2022
See the following for the construction highlights completed during the month of March:
- Grading completed at Soil Nail Shoring Wall
- Drilling and setting of soil nails completed at Soil Nail Wall
- Completed grouting of Soil Nail Wall with shot-crete
February 2022
See the following for the construction highlights completed during the month of February:
- Grading continues for Soil Nail Shoring Wall

- Drilled and set soil nails at Soil Nail Wall
- Grouted of Soil Nail Wall with shot-crete (concrete)
- Backfilled old pool excavation
January 2022
See the following for the construction highlights completed during the month of January:
- Removed additional trees along Crystal Springs Road
- Completed 10'' waterline bypass with concrete collars and thrust blocks
- Removed old waterline pipe
- Began grading slope for Shoring Wall
December 2021
See the following for the construction highlights completed during the month of December:
- Abatement completed, final report being developed
- Trees identified for removal in January 2022
- Contractor poised to install temporary water bypass line (delayed due to inclement weather)
- Stoned construction entrance has been installed to limit tracking mud
- Existing streetlights re-energized